Walter, a Project Manager in a Design Agency, Is Using

question 70

Multiple Choice

Walter, a project manager in a design agency, is using a project management software to manage his project. The agency he works for is currently prioritizing other projects and needs to conserve scarce resources. In the context of priority rules for allocating resources, which of the following rules should Walter use?


Definitions:

Operational Planning

The process of outlining specific procedures and processes aimed at achieving tactical goals within an organization.

Tactical Planning

Short-term, detailed planning that supports strategic planning goals by focusing on achieving specific objectives within a limited time frame.

Strategic Planning

The process of defining the direction and decisions for an organization, including setting goals and determining actions to achieve those goals.

Strategic Planning Process

involves defining a company's strategy or direction and making decisions on allocating its resources to pursue this strategy.