Rachel, a Project Manager, Has Undertaken a Project to Build

question 12

Multiple Choice

Rachel, a project manager, has undertaken a project to build a wall around a compound. She estimates that the cost of materials will be $520 and labor costs will be $10 for 20 hours. If the overheads for this project are 50 percent of the labor and material costs, the total cost will be: