question 11

True/False

As a rule of thumb, the lowest level tasks in a typical project should not take longer than two days to complete.


Definitions:

Split-off

A point in the manufacturing process where multiple products are generated from a common input.

Opportunity Cost

The potential benefit lost when choosing one alternative over another.

Excess Capacity

The amount by which current production capabilities exceed the current demand for a company's products or services.

Performance Evaluation

The process of assessing and reviewing an employee's or an organization's performance against predetermined objectives or criteria.