Robert, a Project Manager, Created a Work Breakdown Structure (WBS)

question 51

Multiple Choice

Robert, a project manager, created a work breakdown structure (WBS) for his new project. He then used the data from the WBS to create a table that assigned responsibilities to each team member and helped organize the project team. In this scenario, Robert created a(n) _____.