Renee, a Project Manager, Is Responsible for Developing a Project

question 31

Multiple Choice

Renee, a project manager, is responsible for developing a project plan for her new project. To do so, she needs to consider all the tasks that would need to be done to produce the deliverable and make a list of them. In this scenario, Renee needs to prepare a(n) _____ for the project.