If the Following Jobs Are Sequenced According to the LPT

question 76

Multiple Choice

If the following jobs are sequenced according to the LPT rule, then the total number of jobs that would be late is (assume zero for today's date) If the following jobs are sequenced according to the LPT rule, then the total number of jobs that would be late is (assume zero for today's date)    A)  5 jobs. B)  4 jobs. C)  3 jobs. D)  2 jobs.