The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Table 9.3
The following table of probabilistic time estimates (in weeks)  and activity predecessors are provided for a project. Table 9.3   - Using Table 9.3, the expected time to complete activity A is A)  5.00 weeks. B)  7.33 weeks. C)  7.67 weeks. D)  8.00 weeks.
- Using Table 9.3, the expected time to complete activity A is