A project consists of the following activities:
A project consists of the following activities:    Table 9.1 -Using Table 9.1,the critical path for this project consists of activities A) A-B-C-D-E-F. B) A-C-E-F. C) A-B-C-F. D) A-B-D-F.
Table 9.1
-Using Table 9.1,the critical path for this project consists of activities