A project consists of the following four activities with activity times in days: Table 9.2
A project consists of the following four activities with activity times in days: Table 9.2   - Using Table 9.2, the earliest finish (EF)  time for activity C is A)  4 days. B)  6 days. C)  10 days. D)  11 days.
- Using Table 9.2, the earliest finish (EF) time for activity C is


Definitions:

Internet

A global network of networks; a communications system.

J1587/1708 Data Bus

A communications protocol used in the automotive industry, particularly in heavy-duty vehicles, for electronic control units to communicate.

CAN 2.0

See Control Area Network. The platform used as the data backbone for CAN-C (auto/light duty) and J1939 (truck/heavy equipment) serial data bus communications.

J1939 Data Bus

A communication network protocol based on CAN (Controller Area Network) designed for heavy-duty vehicle communication, enabling the interchange of electronic data between components.

Related Questions