A Project Consists of the Following Four Activities with Activity

question 12

Multiple Choice

A project consists of the following four activities with activity times in days: Table 9.2
A project consists of the following four activities with activity times in days: Table 9.2   -Using Table 9.2, the critical path for this project is A)  A-B-C. B)  A-C-D. C)  A-B-D. D)  A-B-C-D.
-Using Table 9.2, the critical path for this project is


Definitions: