The Estimated Variance for an Activity with a Most Likely

question 47

Multiple Choice

The estimated variance for an activity with a most likely time (m) equal to 12 weeks,an optimistic time (a) equal to 9 weeks,and a pessimistic time (b) equal to 18 weeks is