A manager wants to analyze the learning curve associated with producing one of his company's products. Accordingly, he has gathered the following data:
A manager wants to analyze the learning curve associated with producing one of his company's products. Accordingly, he has gathered the following data:   Approximately how long will it take to produce the 10<sup>th</sup> unit? A) 1 hour B) 2 hours C) 3 hours D) 4 hours E) 5 hours
Approximately how long will it take to produce the 10th unit?