A manager is trying to estimate the learning rate for a new job. The first unit took 16 hours and the fourth unit required about 13 hours. The learning rate is:


Definitions:

Total Cost

Represents the complete expenditure made by a company in manufacturing a product or offering a service, covering variable and fixed expenses.

Economic Costs

The total cost of choosing one action over another, including both explicit costs and opportunity costs.

Drone

An unmanned aerial vehicle (UAV) that can be remotely controlled or fly autonomously through software-controlled flight plans in embedded systems.

Average Variable Costs

The sum of all variable expenses divided by the total number of units produced.