The Operations Manager for the Blue Moon Brewing Co

question 93

Multiple Choice

The operations manager for the Blue Moon Brewing Co. produces two beers: Lite (L) and Dark (D) . Two of his resources are constrained: production time, which is limited to 8 hours (480 minutes) per day; and malt extract (one of his ingredients) , of which he can get only 675 gallons each day. To produce a keg of Lite beer requires 2 minutes of time and 5 gallons of malt extract, while each keg of Dark beer needs 4 minutes of time and 3 gallons of malt extract. Profits for Lite beer are $3.00 per keg, and profits for Dark beer are $2.00 per keg.
For the production combination of 135 Lite and 0 Dark, which resource is slack (not fully used) ?


Definitions:

Electronically Scanned

The process of analyzing documents or objects with electronic devices to convert information into digital format.

Job-applicant Tracking System

A software application that enables the electronic handling of recruitment and hiring processes by organizing applicant information.

Chronological Resumé

a type of resume that lists work history, education, and other relevant information in reverse chronological order, starting with the most recent experience.

Work History

A record of an individual’s previous employment experiences, including roles, responsibilities, and durations.

Related Questions