The Production Planner for a Private Label Soft Drink Maker

question 67

Multiple Choice

The production planner for a private label soft drink maker is planning the production of two soft drinks: root beer (R) and sassafras soda (S) . Two resources are constrained: production time (T) , of which she has at most 12 hours per day; and carbonated water (W) , of which she can get at most 1,500 gallons per day. A case of root beer requires 2 minutes of time and 5 gallons of water to produce, while a case of sassafras soda requires 3 minutes of time and 5 gallons of water. Profits for the root beer are $6.00 per case, and profits for the sassafras soda are $4.00 per case. For the production combination of 180 root beer and 0 sassafras soda, which resource is slack (not fully used) ?


Definitions:

System Testing

The phase in software testing where a complete, integrated system is tested to verify that it meets the specified requirements.

AON (Activity On Node)

A project management technique where each activity is represented by a node, and arrows represent dependencies, used in critical path and project scheduling analyses.

AOA (Activity On Arrow)

A network diagram convention used in project management to represent activities on arrows and milestones on nodes.

Dummy Activities

Dummy activities are artificial tasks used in project scheduling (e.g., in a PERT or CPM diagram) to establish proper relationships among actual tasks, indicating dependencies without consuming resources or time.