Consider the Following Work Breakdown Structure

question 106

Multiple Choice

Consider the following work breakdown structure:
Consider the following work breakdown structure:   What is the estimated standard deviation in the time for activity D? A) 0 days B) 2 days C) 3 days D) 4 days E) 12 days
What is the estimated standard deviation in the time for activity D?