Consider the Following Work Breakdown Structure

question 13

Multiple Choice

Consider the following work breakdown structure:
Consider the following work breakdown structure:   What is the probability that this project will be completed within 130 days? A) .8413 B) .90 C) .9544 D) .9772 E) .9987
What is the probability that this project will be completed within 130 days?