A PERT/CPM Activity Has an Optimistic Time Estimate of Three

question 25

Multiple Choice

A PERT/CPM activity has an optimistic time estimate of three days, a most likely time estimate of eight days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is