Consider the Following Work Breakdown Structure

question 47

Multiple Choice

Consider the following work breakdown structure:
Consider the following work breakdown structure:   What is the estimated standard deviation in the time for activity E? A) 2 days B) 3 days C) 4 days D) 16 days E) 24 days
What is the estimated standard deviation in the time for activity E?