Consider the Following Work Breakdown Structure

question 29

Multiple Choice

Consider the following work breakdown structure:
Consider the following work breakdown structure:   What is the estimated expected (mean) time for project completion? A) 135 days B) 145 days C) 170 days D) 180 days E) 255 days
What is the estimated expected (mean) time for project completion?


Definitions:

Coefficient Of Correlation

A numerical measure that represents the strength and direction of a linear relationship between two variables.

Covariance

A measure indicating the extent to which two variables change together, revealing whether an increase in one variable tends to be accompanied by an increase (positive covariance) or decrease (negative covariance) in the other.

Distribution

In statistics, a distribution is a function that shows the possible values for a variable and how often they occur.

Correlation Coefficient

A numerical index that gauges the intensity and orientation of the linkage between a pair of variables.

Related Questions