Consider the Following Work Breakdown Structure

question 62

Multiple Choice

Consider the following work breakdown structure:
Consider the following work breakdown structure:   What is the estimated slack time for activity W? A) 0 day B) 25 days C) 35 days D) 45 days E) 85 days
What is the estimated slack time for activity W?