The President of a Consulting Firm Wants to Minimize the Total

question 12

Multiple Choice

The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants-Charlie, Betty, Johnny, and Rick-to complete any of the four projects, as follows:
The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants-Charlie, Betty, Johnny, and Rick-to complete any of the four projects, as follows:   Assume there must be one-to-one matching between consultants and projects. For the optimal schedule, what is the total number of hours it will take these consultants to complete these projects? A) 53 hours B) 46 hours C) 50 hours D) 61 hours E) 54 hours
Assume there must be one-to-one matching between consultants and projects. For the optimal schedule, what is the total number of hours it will take these consultants to complete these projects?


Definitions:

Romanesque Sculpture

Artistic representations from the Romanesque period, characterized by their massive qualities, stylized forms, and often religious themes, emerging in Europe during the 11th and 12th centuries.

Cluniac

Pertaining to a reform movement centered around the Abbey of Cluny in France, founded in 910, emphasizing strict adherence to the Rule of Saint Benedict and influencing European monastic life.

Spiritual Life

An aspect of an individual's existence focused on personal inner beliefs, practices that foster a sense of connection to something greater than oneself.

Covered Courtyard

An architectural feature that includes a courtyard enclosed by a roof or canopy, blending indoor and outdoor spaces.

Related Questions