Which of the following statements is LEAST-Likely true?


Definitions:

Critical Ratio

A scheduling or prioritization technique that calculates the ratio of the time remaining until a task's due date to the time required to complete the task, used to order tasks by urgency.

Due Date

The specified date by which a task, project, or payment is required to be completed or submitted.

Priority Rule

A guideline or criterion used to determine the sequence in which tasks or operations will be carried out in a process or system.

Johnson's Rule

A scheduling rule aimed at minimizing job setup or processing time and the total time to complete a group of jobs on two machines.