Highrise Constructions Ltd Had a Large Three-Year Project with Total

question 2

Multiple Choice

Highrise Constructions Ltd had a large three-year project with total revenue of $5 000 000 and estimated total costs of $4 200 000. The project was 25 per cent complete at the end of the first year, 55 per cent complete at the end of the second year and 100 per cent complete at the end of the third year. Revenues and costs were as estimated. How much profit was earned during the first year if the percentage of completion method was used?


Definitions:

Differential Cost

The difference in total cost that will result from selecting one alternative over another in a decision-making situation.

Differential Cost

The difference in total cost that will result from selecting one choice over another.

Additional Cost

Expenses incurred that are above and beyond the initial forecast or budget for a project or product.

Differential Revenue

The difference in revenue generated under two different scenarios or as a result of a specific action.