As discussed in the Case in Point on Arab spring and oil markets, the regime changes in Tunisia, Egypt, and Libya through 2011 resulted in:


Definitions:

Activity Durations

The estimated time periods that tasks or activities within a project are expected to take to complete.

Project Duration

The total time taken to complete a project from its start to finish, often used in planning and scheduling.

Expected Duration

The estimated time needed to complete a project or task, often considering various uncertainties or risk factors.

Critical Path

A continuity of necessary tasks in a project's agenda that have to be accomplished on time for the project to meet its proposed finalization date.