Examlex

Solved

The Total Completion Time Is 25 Days

question 47

Multiple Choice

The total completion time is 25 days.Task A is planned to take seven days.Task B is planned to take five days.Task C is planned to take eight days.The tasks have a serial relationship.Task A takes nine days to be completed instead of seven days.How much slack does the project have now that Task A is finished?


Definitions:

Hospital Setting

The environment or context of a medical facility where health care services are provided to patients.

Medical Technologist

A healthcare professional responsible for performing laboratory testing critical to the detection, diagnosis, and treatment of disease.

Respiratory Therapist

A healthcare professional specializing in the treatment and care of patients with breathing or other cardiopulmonary disorders.

Related Questions