The Total Completion Time Is 25 Days

question 34

Multiple Choice

The total completion time is 25 days.Task A is planned to take seven days.Task B is planned to take five days.Task C is planned to take eight days.The tasks have a serial relationship.Task A takes nine days to be completed instead of seven days.What are the ES and EF times for Task B now that Task A is complete?