Which of the following is not an example of a variable cost for a manufacturer of bicycles?


Definitions:

Fixed Overhead Cost Variance

The difference between the budgeted fixed overhead costs and the actual fixed overhead incurred.

Variance Analysis

The process of examining differences between actual and budgeted/expected financial performance and investigating the causes.

Flexible Budget

A budget that adjusts or varies with changes in the volume or activity level, providing a more useful tool for performance evaluation.

Standard Costs

Predetermined or estimated costs used to compare with actual costs, serving as a financial management tool for analyzing variances.