Examlex

Solved

Solve Graphically 3x2y=46x+4y=7\begin{array}{c}3 x-2 y=4 \\-6 x+4 y=7\end{array} A) Infinite Number of Solutions
B)

question 17

Multiple Choice

Solve graphically.
- 3x2y=46x+4y=7\begin{array}{c}3 x-2 y=4 \\-6 x+4 y=7\end{array}
 Solve graphically. - \begin{array}{c} 3 x-2 y=4 \\ -6 x+4 y=7 \end{array}    A)  Infinite number of solutions B)   ( 2,1 )   C)  No solution D)   ( 1,2 )


Definitions:

Pessimistic Time

The maximum possible time that a task or project phase is expected to take, assuming worst-case scenarios.

Optimistic Time

The shortest amount of time in which a task or project phase can realistically be completed, assuming everything proceeds better than is normally expected.

Crash Duration

The minimum time period needed to complete an activity or project phase by allocating the maximum resources.

Crash Cost

The additional costs associated with rushing or compressing a project schedule to complete it in the shortest time possible.

Related Questions