Review the PERT Network Below: If It Takes 1, 2

question 42

Multiple Choice

Review the PERT Network below: If it takes 1, 2, or 3 weeks for each activity (represented by a box) to be completed, the critical path is represented by:   Review the PERT Network below: If it takes 1, 2, or 3 weeks for each activity (represented by a box)  to be completed, the critical path is represented by:       A)  the path that begins with  Start  and continues with all boxes labeled with No. 1. B)  the path that begins with  Start,  continues with all boxes labeled with No. 2, and concludes with  Finish.  C)  the path that begins with  Start,  continues with one box labeled with No. 2, proceeds with all boxes labeled with No. 3, and concludes with  Finish.  D)  the path that begins with  Start,  continues with all boxes labeled with No. 1, and concludes with  Finish.  


Definitions:

National Defense

The government activities and measures taken to protect a country and its citizens from external and internal threats, including maintaining armed forces and developing defense strategies.

Positive

Characterized by the presence of something rather than its absence; in economics, often used to describe factual statements or analysis.

Unemployment

The situation when individuals who are capable of working are unable to find a job.

Normative

Relating to principles or rules of right conduct or the distinction between right and wrong; ethical.

Related Questions