Reviewing the PERT Network Below: If It Takes 2 Weeks

question 57

True/False

Reviewing the PERT Network below: If it takes 2 weeks for each activity (represented by a box)to be completed,it can be determined that the boxes labeled with No.1 create the critical path because this path of activities takes the shortest time to complete.