To close a file but leave the application open, use the HOME tab to select the Close option.
Milestone Schedule
A project management tool that outlines the major points or events within a project timeline to help monitor progress.
Negative Float
A situation in project management where the calculated time to complete a set of tasks is less than the time allotted, indicating a project is behind schedule.
Critical Path
The longest sequence of activities in a project plan which must be completed on time for the project to finish on schedule.
Resource Calendar
A document or tool that details the days and times when specific resources are available to work on a project, including personnel and equipment.
Q5: A(n) range is a series of cells.
Q11: Apple developed and launched iOS as an
Q16: Printer speeds are measured in _.<br>A) pages
Q21: When using Windows 8, Charms appear _
Q39: You can use the _ tool to
Q42: You can cut and paste text using
Q52: Basic help information is not stored on
Q55: The Thesaurus tool allows you to translate
Q63: To delete more than one row at
Q71: The VIEW tab includes tools for inserting