When you save the document shown in the figure above for the first time, the ____ dialog box opens.
Project Quality
The degree to which a project meets the requirements, standards, and objectives laid out for it.
Forward Pass
A process that identifies all the early start and early finish times.
Backward Pass
A process that identifies all the late start and late finish times.
Critical Path
In project management, the sequence of stages determining the minimum time to complete a project.