Examlex

Solved

Which New Installation Option Was Introduced in Windows Server 2008

question 29

Multiple Choice

Which new installation option was introduced in Windows Server 2008 that is a bare-bones installation with a limited GUI?


Definitions:

Project Duration

The total time taken to complete a project from its start to finish, often used in planning and scheduling.

Expected Duration

The estimated time needed to complete a project or task, often considering various uncertainties or risk factors.

Critical Path

A continuity of necessary tasks in a project's agenda that have to be accomplished on time for the project to meet its proposed finalization date.

Pessimistic

An attitude or perspective that tends to see the worst aspect of things or believe that the worst will happen.

Related Questions