Technician A says adaptive cruise control system uses a long-range radar sensor. Technician B says the lane departure warning system uses a video camera to measure lane markings. Who is correct?


Definitions:

Critical Paths

The sequence of stages determining the minimum time needed to complete a project, highlighting the most important tasks that directly affect the completion time.

Slack

A measure of the flexibility in scheduling activities; it represents the amount of time that a task in a project can be delayed without causing a delay to subsequent tasks or the project completion date.

PERT

Stands for "Program Evaluation and Review Technique," a project management tool used to schedule, organize, and coordinate tasks within a project.

CPM

Critical Path Method, a project management tool used to schedule, organize, and coordinate tasks within a project. It identifies the longest stretch of dependent tasks and measures the time required to complete them from start to finish.