Identify and give the historical significance of each of the following terms, events, and people in a paragraph or two.
-Socialism
Gantt Chart
A visual project management tool that displays tasks or activities against time.
PERT Chart
is a project management tool used to schedule, organize, and coordinate tasks within a project, standing for Program Evaluation and Review Technique.
Critical Path Method
A project management technique that identifies the longest sequence of dependent tasks and calculates the shortest possible project duration.
Program Evaluation
The systematic collection and analysis of information about the activities, characteristics, and outcomes of programs to make judgments about them, to improve effectiveness, and/or to inform decisions about future programming.
Q12: In 1893,American sugar growers orchestrated the overthrow
Q13: bracero program<br>A)interventionists<br>B)opposed to colonialism<br>C)Big Three meeting<br>D)blamed businesspeople
Q40: The Wagner Act:<br>A) created the Works Progress
Q41: What accounted for the tension between Great
Q44: Under the 1924 Immigration Act,no Asians were
Q80: American standard of living
Q87: Scientific management
Q87: In the United States during World War
Q88: José Martí<br>A)advocate of free silver<br>B)president of the
Q121: In 1940,the "cash and carry" plan:<br>A) allowed