A company has performance and regulatory requirements that call for it to run its workload only in its on-premises data center. Which AWS services or resources should the company use? (Choose two.)
Projected Output Rate
An estimated rate of production for future periods based on current data and trends, forecasting the volume of output.
Record Accuracy
The degree to which records are complete, correct, and reliable.
MRP
Material Requirements Planning, a system for inventory and production planning that ensures materials and products are available for production and delivery to customers.
Successful MRP
Refers to the effective implementation and management of Material Requirements Planning, a system for efficiently managing the manufacturing process through inventory control and production scheduling.
Q5: A company has an encrypted Amazon Redshift
Q76: A company has a production environment running
Q106: A company runs its business-critical web application
Q126: A company is considering a move to
Q134: A company is about to launch a
Q344: A retail company wants to provision only
Q436: What is one of the core principles
Q472: The user is fully responsible for which
Q505: What does the AWS Simple Monthly Calculator
Q792: A pharmaceutical company operates its infrastructure in