Given the Portion of the Network Diagram Shown Below,where Numbers

question 55

Multiple Choice

Given the portion of the network diagram shown below,where numbers in boxes show the task times,what is the earliest finish time for task C,if the earliest start time for task A is 10,and the earliest start time for task B is 13? Given the portion of the network diagram shown below,where numbers in boxes show the task times,what is the earliest finish time for task C,if the earliest start time for task A is 10,and the earliest start time for task B is 13?   A) 13 B) 16 C) 20 D) 24


Definitions:

Economic Profits

Profits earned by a firm after accounting for both explicit and implicit costs, indicating the total returns exceeding the costs of all resources employed.

Economic Profit

The difference between a firm's total revenue and its total costs, including both the explicit and implicit costs, representing the financial gain exceeding the opportunity costs.

Total Revenue

The gross income of a company, which is the sum of money generated from its goods or services sold before deducting any costs.

Annual Salary

The total amount of money earned by an employee in a year from their job before taxes and other deductions.

Related Questions