There Are Four Parallel Paths on a Network Diagram

question 417

Multiple Choice

There are four parallel paths on a network diagram. The summary duration of each path is below: A, C, G: 10 weeks A, B, F: 8 weeks D, E, H: 12 weeks D, B, F: 7 weeks Which of the following tasks are on the critical path?