A project team has completed a major deliverable earlier than planned and wants to deliver it for testing. The team lead sends an email providing notice of task completion to the project manager. Which of the following describes how the project manager can increase the likelihood that the deliverable moves to testing?
Nods While Speaking
A nonverbal cue often indicating agreement or reinforcing the speaker's point, used during verbal communication.
Points of Disagreement
Specific areas or topics where opinions or perceptions diverge or conflict between two or more parties.
Listener's Agreement
The act of a listener showing understanding, acceptance, or approval of what is being communicated.
Skilled Active Listeners
Individuals proficient in fully engaging with and understanding spoken communication.
Q41: A company hires a number of interns
Q64: A network engineer is planning to connect
Q70: A project coordinator notices there is a
Q114: A non-stakeholder approaches the project manager and
Q116: Given the following: http://example.com/download.php?id-.../.../.../etc/passwd Which of the
Q130: A company hires a penetration tester to
Q142: A network technician has installed multiple new
Q349: A Chief Executive Officer (CEO) has approached
Q429: A project manager has been assigned a
Q447: While working on risk ranking, the project