Tasks A, B, and C Have a Duration of Two

question 321

Multiple Choice

Tasks A, B, and C have a duration of two days. Task D has a duration of three days, and Task E has duration of four days. Task A starts on Day 1, and Task B starts on Day 2. Task C starts after Task A. Tasks D and E start after Task C. Which of the following is the critical path if Task B starts on Day 3?