A project sponsor wants to know when the plan changed to ship the deliverables to a new location. To determine the answer, the project manager should FIRST review the:


Definitions:

Conclusions Section

The part of a document or presentation that summarizes the key findings, implications, and recommendations based on the discussed material.

Collected Data

Information that has been gathered through observation, experimentation, surveys, or other methodologies for analysis and decision-making.

Specific Actions

Detailed steps or measures to be taken in order to achieve a particular goal or resolve an issue.

Decision Matrix

A tool used to compare and prioritize a list of options or variables based on a set of criteria.

Related Questions