Based on the Table Below: Which of the Following

question 24

Multiple Choice

Based on the table below: Based on the table below:   Which of the following is the critical path if Task B has extended to ten days? A)  21 days B)  23 days C)  24 days D)  26 days Which of the following is the critical path if Task B has extended to ten days?