A program manager informs a project manager that a new, high-priority project has been approved and will need the current project's resources before the scheduled project close date. The project team meets and determines that the project should be fast-tracked. Which of the following documents should the project team reference to fast-track the project? (Choose two.)


Definitions:

Communication Process

The transmission of information and understanding from one person to another, involving a sender, message, medium, receiver, and feedback.

Communication Process

The series of steps through which information is transmitted and received between senders and receivers, including encoding, medium of transmission, decoding, and feedback.

Fields of Experience

Areas or domains in which an individual or organization has gained knowledge or skills through direct involvement or practice.

Feedback Loop

A system used to gather and use information about a product's performance to make improvements or adjustments.