Task A starts on Day 1 and has a duration of two days. Task B has a duration of two days and starts on Day 3. Task C starts after Task A and has a duration of three days. Task D starts after Task B and Task C and has a duration of one day. Which of the following represents the critical path?
Goal Achievement
The successful attainment of specific aims or objectives.
Scientific Research
The organized examination and analysis of data and sources to determine truths and achieve fresh insights.
Leadership Traits
Characteristics or qualities that are typically seen in effective leaders, such as integrity, decisiveness, empathy, and resilience.
World War I
A global conflict that took place primarily in Europe from 1914 to 1918, involving many of the world's great powers and marking significant shifts in military and geopolitical landscapes.
Q7: A penetration tester gains access to a
Q67: A manufacturer is developing a product that
Q91: A PM is asked to keep the
Q114: An email sent from the Chief Executive
Q151: Which of the following project management roles
Q163: Many questions have arisen regarding a newly
Q202: A project is running behind schedule. To
Q225: A project manager is overseeing a multinational
Q271: A post implementation review is being performed
Q389: A network engineer is deploying a new