A Project Manager Is Meeting with Top Management Executives and Presenting

question 232

Multiple Choice

A project manager is meeting with top management executives and presenting a project status report. The Chief Information Officer (CIO) and other executives complain that the meeting is taking too long and not providing summary information on the project's progress. Which of the following should the project manager be presenting?