You are the project manager of the NHH project for your company. You have completed the first round of risk management planning and have created four outputs of the risk response planning process. Which one of the following is NOT an output of the risk response planning?


Definitions:

Policies

Strategies or courses of action adopted and pursued by an organization, government, or individual.

Composition

The manner in which something is constituted, arranged, or planned, including the structure of a piece of writing, music, or the arrangement of elements in a work of art.

Leadership

The process of influencing the activities of an organized group toward goal achievement, requiring a combination of personality traits, managerial skills, and strategic vision.

Policies

Principles, rules, or guidelines formulated or adopted by an organization, government, or individual to achieve a desired outcome.