Your organization has a project that is expected to last 20 months but the customer would really like the project completed in 18 months. You have worked on similar projects in the past and believe that you could fast track the project and reach the 18 month deadline. What increases when you fast track a project?
Third Party
An individual or group aside from the two primarily involved in a situation, agreement, or transaction, often providing additional services or playing a neutral role.
Principal
The primary party involved in a contractual agreement or the original amount of money lent or invested before interest.
Agent
An individual or entity authorized to act on behalf of another person or entity in dealings with third parties.
Principal Negotiator
identifies a person who has the primary responsibility for conducting negotiations, often on behalf of an organization or government.
Q70: Which of the following DoD directives defines
Q71: An administrator notices that a long-running script,
Q74: Other than cost savings realized due to
Q85: Which of the following RMF phases identifies
Q109: A systems administrator manually added a new
Q131: A junior systems administrator is upgrading a
Q274: When beginning an audit, both the system
Q410: Which of the following is NOT one
Q425: Which of the following is not a
Q474: Which United States law is focused on