Assume You Are Sequencing Jobs Using Johnson's Rule

question 59

Multiple Choice

Assume you are sequencing jobs using Johnson's rule.There are three jobs called A, B and C.The first step in assembling and the second step is painting. Job A requires 3 hours to assemble and 6 hours to paint.Job B requires 7 hours to assemble and 2 hours to paint.Job C requires 4 hours to assemble and 1 hour to paint.The objective is to minimize the total processing time of all jobs, using Johnson's rule.What is the correct sequence to process the jobs?


Definitions:

Simple Interest

Interest calculated on the principal amount of a loan or deposit without compounding.

Daily Closing Balance

The total amount in an account at the end of each day, taking into account all transactions and activities of that day.

Bank Account

A financial account maintained by a bank or other financial institution in which the financial transactions between a customer and the bank are recorded.

Discounted

A reduction applied to the price of goods, services, or securities, or the process of calculating the present value of a series of future cash flows.

Related Questions