To Complete a Contract for Fitting Out a New Shop

question 3

Multiple Choice

To complete a contract for fitting out a new shop in time for its opening, a refurbishment company has employed three temporary painters for 10 days at £45 per day and moved two carpenters who are paid £70 per day from another job for three days. The penalty for late completion of the shop is £300 but the delay to the carpenters' current job will only cost £150. What are the relevant costs?